Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.

This research project aimed to carry out the analysis of the electrical system of the company Genim S.A .; The same one that has had an unplanned growth of the electrical demand, which is manifested in an unknown loadability of the current transformer, which has generated problems in the quality of...

Celý popis

Uloženo v:
Podrobná bibliografie
Hlavní autor: Palomo Gadvay, Diego Alexis (author)
Další autoři: Quinatoa Toapanta, Washington Paul (author)
Médium: bachelorThesis
Jazyk:spa
Vydáno: 2017
Témata:
On-line přístup:http://repositorio.utc.edu.ec/handle/27000/4470
Tagy: Přidat tag
Žádné tagy, Buďte první, kdo vytvoří štítek k tomuto záznamu!
_version_ 1859064027450179584
author Palomo Gadvay, Diego Alexis
author2 Quinatoa Toapanta, Washington Paul
author2_role author
author_facet Palomo Gadvay, Diego Alexis
Quinatoa Toapanta, Washington Paul
author_role author
collection Repositorio Universidad Técnica de Cotopaxi
dc.contributor.none.fl_str_mv Marrero, Secundino
dc.creator.none.fl_str_mv Palomo Gadvay, Diego Alexis
Quinatoa Toapanta, Washington Paul
dc.date.none.fl_str_mv 2017-08
2018-05-08T19:48:23Z
2018-05-08T19:48:23Z
dc.format.none.fl_str_mv 38 páginas
application/pdf
dc.identifier.none.fl_str_mv Palomo Gadvay, D. A. (2017). Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017. Latacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de Potencia
PI-000592
http://repositorio.utc.edu.ec/handle/27000/4470
dc.language.none.fl_str_mv spa
dc.publisher.none.fl_str_mv Latacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de Potencia
dc.rights.none.fl_str_mv http://creativecommons.org/licenses/by-nc-sa/3.0/ec/
info:eu-repo/semantics/openAccess
dc.source.none.fl_str_mv reponame:Repositorio Universidad Técnica de Cotopaxi
instname:Universidad Técnica de Cotopaxi
instacron:UTC
dc.subject.none.fl_str_mv INGENIERÍA ELÉCTRICA
SISTEMA ELÉCTRICO
DEMANDA ELÉCTRICA
MEDICIONES
dc.title.none.fl_str_mv Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
dc.type.none.fl_str_mv info:eu-repo/semantics/publishedVersion
info:eu-repo/semantics/bachelorThesis
description This research project aimed to carry out the analysis of the electrical system of the company Genim S.A .; The same one that has had an unplanned growth of the electrical demand, which is manifested in an unknown loadability of the current transformer, which has generated problems in the quality of voltage, power cuts by actuation of the electrical protections. This is why the objective is to determine the factors that currently produce low power quality in the electricity supply, by collecting information and obtaining measurements of the electrical system, this with the installation of a Fluke 435 load analyzer in the bus bars. General board, the same that reflected data of power, voltage, current, power factor. These measurements allowed to perform frequency histograms the same ones that were simulated in Etap software. Once the simulations were carried out, the electrical parameters of the industrial plant were known, resulting in the voltage levels being outside the 2% allowed by the regulation, in addition to that the transformer was within normal operating percentages At half-load with a value of 30.72 [KVA], because if the whole transformer was used, the transformer was overloaded, making it impossible to satisfy the demand of 92.25 [KVA]. Allows to satisfy the load to be implemented and according to the needs of the food processing plant to avoid the power cuts by overload and by voltage profiles.
eu_rights_str_mv openAccess
format bachelorThesis
id UTC_bfee93a80a7876f82cd29e2e53590976
identifier_str_mv Palomo Gadvay, D. A. (2017). Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017. Latacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de Potencia
PI-000592
instacron_str UTC
institution UTC
instname_str Universidad Técnica de Cotopaxi
language spa
network_acronym_str UTC
network_name_str Repositorio Universidad Técnica de Cotopaxi
oai_identifier_str oai:repositorio.utc.edu.ec:27000/4470
publishDate 2017
publisher.none.fl_str_mv Latacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de Potencia
reponame_str Repositorio Universidad Técnica de Cotopaxi
repository.mail.fl_str_mv .
repository.name.fl_str_mv Repositorio Universidad Técnica de Cotopaxi - Universidad Técnica de Cotopaxi
repository_id_str 0
rights_invalid_str_mv http://creativecommons.org/licenses/by-nc-sa/3.0/ec/
spelling Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.Palomo Gadvay, Diego AlexisQuinatoa Toapanta, Washington PaulINGENIERÍA ELÉCTRICASISTEMA ELÉCTRICODEMANDA ELÉCTRICAMEDICIONESThis research project aimed to carry out the analysis of the electrical system of the company Genim S.A .; The same one that has had an unplanned growth of the electrical demand, which is manifested in an unknown loadability of the current transformer, which has generated problems in the quality of voltage, power cuts by actuation of the electrical protections. This is why the objective is to determine the factors that currently produce low power quality in the electricity supply, by collecting information and obtaining measurements of the electrical system, this with the installation of a Fluke 435 load analyzer in the bus bars. General board, the same that reflected data of power, voltage, current, power factor. These measurements allowed to perform frequency histograms the same ones that were simulated in Etap software. Once the simulations were carried out, the electrical parameters of the industrial plant were known, resulting in the voltage levels being outside the 2% allowed by the regulation, in addition to that the transformer was within normal operating percentages At half-load with a value of 30.72 [KVA], because if the whole transformer was used, the transformer was overloaded, making it impossible to satisfy the demand of 92.25 [KVA]. Allows to satisfy the load to be implemented and according to the needs of the food processing plant to avoid the power cuts by overload and by voltage profiles.Este proyecto de investigación se encaminó a realizar el análisis del sistema eléctrico de la empresa Genim S.A.; la misma que ha tenido un crecimiento no planificado de la demanda eléctrica, lo cual se manifiesta en una cargabilidad desconocida del transformador actual por lo que ha generado problemas en la calidad de voltaje, cortes de energía por actuación de las protecciones eléctricas. Es por esto que el objetivo es determinar los factores que actualmente producen baja calidad de energía en el suministro eléctrico, mediante la recopilación de información y obtención de mediciones del sistema eléctrico, esto con la instalación de un analizador de carga Fluke 435 en las barras del tablero general, el mismo que reflejó datos de potencia, voltaje, corriente, factor de potencia. Estas mediciones permitieron realizar histogramas de frecuencia los mismos que fueron simulados en el software Etap. Una vez realizado las simulaciones se llegó a conocer los parámetros eléctricos de la planta industrial, dando como resultado que los niveles de voltaje se encontraban fuera del 2 % permitido por la regulación, además de que el transformador se encontraba dentro de los porcentajes normales de funcionamiento a media carga con un valor de 30,72 [KVA] ya que si se trabaja a toda su capacidad el transformador se encontraba sobrecargado, haciendo imposible satisfacer la demanda de 92,25 [KVA], por lo que se planteó un diseño eléctrico que permita satisfacer la carga a implementarse y acorde a las necesidades de la planta procesadora de alimentos para evitar los cortes de energía por sobre carga y por perfiles de voltaje.Universidad Técnica de CotopaxiLatacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de PotenciaMarrero, Secundino2018-05-08T19:48:23Z2018-05-08T19:48:23Z2017-08info:eu-repo/semantics/publishedVersioninfo:eu-repo/semantics/bachelorThesis38 páginasapplication/pdfPalomo Gadvay, D. A. (2017). Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017. Latacunga: Universidad Técnica de Cotopaxi; Facultad de Ciencias de la Ingeniería y Aplicadas; Ingeniería Eléctrica en Sistemas Eléctricos de PotenciaPI-000592http://repositorio.utc.edu.ec/handle/27000/4470spahttp://creativecommons.org/licenses/by-nc-sa/3.0/ec/info:eu-repo/semantics/openAccessreponame:Repositorio Universidad Técnica de Cotopaxiinstname:Universidad Técnica de Cotopaxiinstacron:UTC2018-05-09T08:00:16Zoai:repositorio.utc.edu.ec:27000/4470Institucionalhttp://repositorio.utc.edu.ec/Universidad públicahttps://www.utc.edu.ec/..Ecuador...opendoar:02026-03-08T03:37:28.084004Repositorio Universidad Técnica de Cotopaxi - Universidad Técnica de Cotopaxitrue
spellingShingle Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
Palomo Gadvay, Diego Alexis
INGENIERÍA ELÉCTRICA
SISTEMA ELÉCTRICO
DEMANDA ELÉCTRICA
MEDICIONES
status_str publishedVersion
title Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
title_full Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
title_fullStr Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
title_full_unstemmed Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
title_short Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
title_sort Análisis de la demanda eléctrica actual para la ampliación del sistema eléctrico en la planta procesadora de alimentos Genim S.A. del cantón Latacunga en el año 2017.
topic INGENIERÍA ELÉCTRICA
SISTEMA ELÉCTRICO
DEMANDA ELÉCTRICA
MEDICIONES
url http://repositorio.utc.edu.ec/handle/27000/4470